Breast Test Wales

This slideshow requires JavaScript.

Phillips Services have just completed the upgrading of the critical mains supply at Breast Test Wales in Swansea. The works had to take place over a scheduled shutdown in out of hours so as not to affect the operation of the clinic. Due to the sensitive nature of the equipment installed at the clinic, we had to liaise with other specialist organisations to ensure that everything was shutdown and restarted correctly and in line with the new system.

The site had been experiencing fluctuations and spikes in its main supply and as such as part of the upgrading works, we installed a voltage optimiser to ensure that the voltage did not exceed the required amounts. Prior to the installation the spikes in supply had caused several equipment failures at a huge financial cost to the centre.

Working with McCanns who designed the system, we supplied and installed the following;

  • Mains Incoming Panel
  • Voltage Optimiser
  • 4 x New Distribution Boards
  • Surge Protection Units

 

 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s